Vinyl Tile Install in a Large Church

Original flooring was old carpeting that showed lots of wear and tear.
First day we went in there with with automatic floor scrapers to scrape up the old carpet and glue
Once the carpet and glue was cleaned up off the floor, rebuilding of the handicap ramp took place.  First step was to tear out the old ramp.
Once the old ramp was removed, it was time to build the new one.  This included widening the ramp to twice the size of the existing ramp.
Now, that the ramp rebuild is completed, we can move onto laying the tile.  A cross inlay was done in the middle of the room.  This cross was a lighter color tile, than the outside.  So the first step was to layout the cross and lay that tile.
Once the cross pattern was completed, it was now time to move onto the rest of the tile. 
The floor was completed several days after we had begun work.  Even though the floor was down, there was still work that had to be done.  IE: cove base and sealing of the tile